Friday, October 8, 2010

The contractor will continue with storm sewer work next week. The contractor will also continue with hot-mix asphalt pavement patching, earth excavation and aggregate base course preparation into next week. The contractor is also scheduled to install the concrete curb and gutter on the east side of Greenwood Road (from #907 to #901 – south of Glenview Road and from Jiffy Lube to Springdale Road) next week. Water main work is scheduled to start in mid-October.