Friday, September 17, 2010

All storm sewer on the east side of Greenwood Road, south of Glenview Road has been completed.

Two sewer crews will continue to work on the storm sewer installation on the east side of Greenwood Road, north of Glenview Road.

The contractor is scheduled to start water main work on Glenview Road, east of Greenwood Road mid- to late next week (weather permitting). Between the hours of 9:00 A.M. and 3:00 P.M. eastbound traffic on Glenview Road will be shifted into the left turn lanes.