Friday, October 22, 2010


The contractor will continue with storm sewer work on Glenview (west of Greenwood) next week. Water main work is scheduled to continue next week on Glenview Road. The contractor will also continue with aggregate base course preparation into next week. The contractor is also scheduled to complete curb and gutter and sidewalk installation (see photo of sidewalk installation) in various locations along the east side of Greenwood Road next week.

Friday, October 15, 2010

The contractor will continue with storm sewer work next week. Water main work is scheduled to start in next week on Glenview Road. Glenview Road between Greenwood and Glenshire will be closed on Wednesday. Westbound and eastbound Glenview traffic will be detoured via Shermer, Central and Greenwood.

The contractor will also continue with hot-mix asphalt pavement patching, earth excavation and aggregate base course preparation into next week. The contractor is also scheduled to install the concrete curb and gutter on the east side of Greenwood Road (from #907 to #901 – south of Glenview Road and from Jiffy Lube to Springdale Road) next week.

Friday, October 8, 2010

The contractor will continue with storm sewer work next week. The contractor will also continue with hot-mix asphalt pavement patching, earth excavation and aggregate base course preparation into next week. The contractor is also scheduled to install the concrete curb and gutter on the east side of Greenwood Road (from #907 to #901 – south of Glenview Road and from Jiffy Lube to Springdale Road) next week. Water main work is scheduled to start in mid-October.

Friday, October 1, 2010


The contractor will continue with storm sewer work next week (see photograph for storm sewer installation). The contractor will also continue with hot-mix asphalt pavement patching, earth excavation and aggregate base course preparation into next week. Water main work is scheduled to start in mid-October.