The contractor is scheduled to stop (suspend) work this week for the winter. This week, the contractor is scheduled to install signs and complete clean up work in preparation for the winter.

Monday, November 22, 2010

The contractor is scheduled to stop (suspend) work this week for the winter. This week, the contractor is scheduled to continue with hot-mix asphalt pavement patching, temporary asphalt driveways and sidewalks in various locations throughout the project and finish the temporary pavement markings.

Wednesday, November 10, 2010

The contractor will continue with storm sewer and water services this week and into next week. The contractor is also scheduled to continue with hot-mix asphalt pavement patching, temporary asphalt driveways and ramps, concrete road base course, curb and gutter and sidewalk installation in various locations along the east side of Greenwood Road this week and into next week.

Friday, November 5, 2010

The contractor will continue with storm sewer and water main work on Glenview (west of Greenwood) this week and into next week. The contractor is also scheduled to continue with hot-mix asphalt pavement patching, concrete road base course, curb and gutter and sidewalk installation in various locations along the east side of Greenwood Road this week and into next week.

Monday, November 1, 2010

The contractor will continue with storm sewer and water main work on Glenview (west of Greenwood) this week. The contractor is also scheduled to continue with concrete road base course, curb and gutter and sidewalk installation in various locations along the east side of Greenwood Road this week.