Friday, December 2, 2011

Construction of this project is complete.

Wednesday, October 19, 2011

This project is nearing completion with only cleanup and punch list work remaining.

Friday, October 14, 2011

This project is nearing completion with only cleanup and punch list work remaining.

Friday, October 7, 2011

This project is nearing completion with only cleanup and punch list work remaining.

Friday, September 30, 2011

This project is nearing completion with only cleanup and punch list work remaining.

Friday, September 23, 2011

Countryside Industries (Landscaper) has completed sod and topsoil placement. This project is nearing completion with only punch list work remaining.

Friday, September 16, 2011

Countryside Industries (Landscaper) has started placing topsoil this week and will continue with topsoil and sod placement into next week.

Friday, September 9, 2011

Countryside Industries (Landscaper) has started placing topsoil this week and will continue with topsoil and sod placement into next week.

Friday, September 2, 2011

This project is nearing completion with only punch list work, topsoil and sodding remaining. Topsoil and sodding is scheduled to be placed in September.

Friday, August 26, 2011

This project is nearing completion with only punch list work, topsoil and sodding remaining. Topsoil and sodding is scheduled to be placed in September.

Friday, August 19, 2011

This project is nearing completion with only punch list work, topsoil and sodding remaining. Topsoil and sodding is scheduled to be placed in September.

Friday, August 12, 2011

Next week, the contractor is scheduled to continue with minor utility work (structure adjustments, etc.) and punch list work. Topsoil and sodding is scheduled to be placed in September.

Friday, August 5, 2011

Next week, the contractor is scheduled to work on minor utility work (structure adjustments, etc.), parkway grading, clean up and punch list work. Topsoil and sodding is scheduled to be placed in September.

Friday, July 29, 2011

This week the electrical contractor, Home Towne Electric has activated the new traffic signal. This week the concrete contractor is looking to finish all the concrete work (sidewalks, curb and gutter and driveways) on the project. Late this week and early next week, the general contractor, Schroeder Asphalt is planning on working on parkway grading and driveway replacement.

Friday, July 22, 2011

This week and late next week, the electrical contractor, Home Towne Electric is scheduled to continue with traffic signal work. Next week, the general contractor, Schroeder Asphalt is planning on working on driveway replacement.

Friday, July 15, 2011

This week and next week, the contractor is working on curb and gutter and sidewalk work construction along Greenwood Road. Late next week, the contractor is planning on working on driveway replacement.

Friday, July 8, 2011

Today (Friday), tomorrow (Saturday) and Monday, Schroeder Asphalt will be paving the hot-mix asphalt surface course. This week and next week, the contractor also working to complete a majority of the curb and gutter, driveway and sidewalk construction along Greenwood Road (south of Glenview Road).

Thursday, June 30, 2011

This week Schroeder Asphalt will be completing a majority of the asphalt binder course paving. Late this week and possibly into early next week, Home Towne Electric will resume with traffic signal related work. Next week, the contractor is scheduled to resume curb and gutter and sidewalk construction along Greenwood Road (south of Glenview Road).

Friday, June 24, 2011

This week Schroeder Asphalt completed a majority of the sidewalk west of Greenwood and will be paving the polymerized leveling binder on the west side of Greenwood Road. Next week, Shroeder Asphalt is scheduled to pave the asphalt binder course on the west side of Greenwood Road (weather permitting) and traffic signal related work will recommence.

Thursday, June 16, 2011

The concrete contractor is scheduled to complete the curb and gutter and concrete base course installation on the west side of Greenwood Road this week. Next week, Schroeder Asphalt is scheduled to pave the asphalt binder course on the west side of Greenwood Road (weather permitting).

Friday, June 10, 2011

The sewer contractor is scheduled to be complete with storm sewer work on the west side of Greenwood Road (south of Glenview Road) next week. The concrete contractor will continue with curb and gutter and concrete base course installation on the west side of Greenwood Road into next week.

Friday, June 3, 2011

The sewer contractor is scheduled to be complete with storm sewer work on the west side of Greenwood Road (south of Glenview Road) next week. The concrete contractor will continue with curb and gutter and concrete base course installation on the west side of Greenwood Road.

Friday, May 27, 2011

Next week the contractor will continue with storm sewer work on the west
side of Greenwood Road (south of Glenview Road). The concrete
contractor will continue with curb and gutter and concrete base course
installation along the west side of Greenwood Road next week.

Monday, May 9, 2011

The contractor is scheduled to resume hot-mix asphalt paving this week. The electrical contractor will also be continuing with traffic signal work this week.

Please know that traffic patterns are scheduled to change mid-week (weather permitting) when the contractor moves to the next stage of construction. Late this week, the contractor is scheduled to begin excavation on the west side of Greenwood Road.

Saturday, April 30, 2011

The concrete contractor has completed the majority of the concrete work within the intersection and will return at a later date to complete the concrete work on the west side of Greenwood Road. The asphalt contractor has milled the east side of Greenwood Road and all of Glenview Road in preparation for asphalt paving starting late this week and carrying into next week. Additionally, the electrical contractor will be onsite working on the traffic signals at the intersection.

Thursday, April 21, 2011

The contractor continued with placement of curb and gutter and concrete road base this week. The contractor will also be placing temporary asphalt pavement on the east side of Greenwood Road (south of Glenview) late this week and/or early next week. Please be alert to traffic control signage and markings as traffic patterns may change late next week or early the following week.

Friday, April 15, 2011

The sewer contractor has completed the installation of water services this week. The concrete contractor will continue placing curb and gutter and concrete road base at the intersection of Glenview Road and Greenwood Road into next week. The contractor will also be placing temporary asphalt pavement widening on the east side of Greenwood Road (south of Glenview) next week. Please be alert to traffic control signage and markings as traffic patterns may change late next week or early the following week.

Friday, April 8, 2011

The sewer contractor will continue installation of water services next week. The concrete contractor will be onsite next week to continue placing curb and concrete road base at the intersection of Glenview Road and Greenwood Road. Additionally, earth excavation for the new road base will continue on Glenview Road.

Friday, April 1, 2011

The sewer contractor will continue installation of water services next week. The concrete contractor will be onsite next week to begin placing curb and concrete road base at the intersection of Glenview Road and Greenwood Road. Additionally, earth excavation for the new road base and the installation of electrical conduit for the new traffic signals is scheduled to start.

Tuesday, March 29, 2011

Water service work this week

Water service work has begun on Greenwood Road. The service line from the water main to the yard shutoff valve (b-box) is being upgraded to a 1.5 inch diameter capacity for each home that currently has a smaller service line. Water service will be disrupted for a short time (up to 4 hours) during the day when the connection is made to the water main. Notices will be provided in advance of the water service disruption to allow you preparation time. If water appears discolored after the installation, please allow your faucet to run for several minutes beyond when the water flows clear. If no one is home when service is resumed, the Contractor will attempt to locate an outside hose faucet and turn it on to allow for clearing your system.

Thursday, March 17, 2011

Work has recommenced!

Construction activities have started this week with traffic relocated to
the west side of Greenwood. Base course and curb excavation is in
progress and installation will start next week. Water service line work
will also begin next week and service disruption notices will be
provided in advance to those affected properties.

Project construction is anticipated to be complete by June 2011.