Friday, April 15, 2011

The sewer contractor has completed the installation of water services this week. The concrete contractor will continue placing curb and gutter and concrete road base at the intersection of Glenview Road and Greenwood Road into next week. The contractor will also be placing temporary asphalt pavement widening on the east side of Greenwood Road (south of Glenview) next week. Please be alert to traffic control signage and markings as traffic patterns may change late next week or early the following week.