Thursday, June 30, 2011

This week Schroeder Asphalt will be completing a majority of the asphalt binder course paving. Late this week and possibly into early next week, Home Towne Electric will resume with traffic signal related work. Next week, the contractor is scheduled to resume curb and gutter and sidewalk construction along Greenwood Road (south of Glenview Road).

Friday, June 24, 2011

This week Schroeder Asphalt completed a majority of the sidewalk west of Greenwood and will be paving the polymerized leveling binder on the west side of Greenwood Road. Next week, Shroeder Asphalt is scheduled to pave the asphalt binder course on the west side of Greenwood Road (weather permitting) and traffic signal related work will recommence.

Thursday, June 16, 2011

The concrete contractor is scheduled to complete the curb and gutter and concrete base course installation on the west side of Greenwood Road this week. Next week, Schroeder Asphalt is scheduled to pave the asphalt binder course on the west side of Greenwood Road (weather permitting).

Friday, June 10, 2011

The sewer contractor is scheduled to be complete with storm sewer work on the west side of Greenwood Road (south of Glenview Road) next week. The concrete contractor will continue with curb and gutter and concrete base course installation on the west side of Greenwood Road into next week.

Friday, June 3, 2011

The sewer contractor is scheduled to be complete with storm sewer work on the west side of Greenwood Road (south of Glenview Road) next week. The concrete contractor will continue with curb and gutter and concrete base course installation on the west side of Greenwood Road.