Friday, July 29, 2011

This week the electrical contractor, Home Towne Electric has activated the new traffic signal. This week the concrete contractor is looking to finish all the concrete work (sidewalks, curb and gutter and driveways) on the project. Late this week and early next week, the general contractor, Schroeder Asphalt is planning on working on parkway grading and driveway replacement.

Friday, July 22, 2011

This week and late next week, the electrical contractor, Home Towne Electric is scheduled to continue with traffic signal work. Next week, the general contractor, Schroeder Asphalt is planning on working on driveway replacement.

Friday, July 15, 2011

This week and next week, the contractor is working on curb and gutter and sidewalk work construction along Greenwood Road. Late next week, the contractor is planning on working on driveway replacement.

Friday, July 8, 2011

Today (Friday), tomorrow (Saturday) and Monday, Schroeder Asphalt will be paving the hot-mix asphalt surface course. This week and next week, the contractor also working to complete a majority of the curb and gutter, driveway and sidewalk construction along Greenwood Road (south of Glenview Road).